48.3 F
Washington D.C.
Saturday, November 9, 2024

GAO: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes

Multiple factors affect the time it takes to finalize a construction contract change. For example, preparing cost estimates can be time consuming, particularly for complex changes. Yet the time may be used to help ensure the government has adequate cost data to inform negotiations. In addition, according to agency officials, miscommunication during the contract change process—which can lead to problems such as unauthorized work undertaken by the contractor—can result in additional reviews and longer time frames. According to U.S. Army Corps of Engineers (USACE) data, most of its construction contract changes are finalized within 60 days. Some take much longer, however.

Agency officials and industry representatives agreed that perceptions differ about the length of the contract change process. For example, because a change can impact the contractor’s cost and schedule immediately, the contractor typically perceives that the process starts earlier—and lasts longer—than the government does.

Neither GSA nor USACE regularly monitors how long it takes to finalize construction contract changes, limiting management’s ability to identify and respond to problems. Internal controls require agencies to collect and use quality data for management purposes such as monitoring agency activities. GSA systems do not collect data that permit analysis of contract change timeframes at the headquarters level. USACE systems produce contract change data for its districts, but data consolidation and calculations must be done manually and are not done regularly. Neither agency has a strategy in place to address these issues. Without regular review of these timeframes, USACE and GSA contracting officials may be unaware of any existing or potential problems, such as long process times that may affect project schedules. In addition, these data system limitations are likely to create difficulties for agencies when providing the information required by new legislation.

In fiscal year 2018, federal agencies spent more than $36 billion on construction contracts, with more than 45 percent going to small business. Typically, construction projects involve some degree of change as the project progresses. Some federal construction contractors have raised concerns that delays in processing contract changes and making payments creates challenges, particularly for small businesses. Section 855 of the National Defense Authorization Act for Fiscal Year 2019 requires agencies to report information related to how quickly they finalize contract changes.

GAO was asked to review federal construction contract change processes and timeframes. GAO (1) identified factors that affect the time it takes to finalize contract changes, and (2) assessed the extent to which selected agencies monitor time frames for finalizing contract changes. GAO reviewed relevant regulations and agency policies, analyzed available data, and interviewed officials from GSA’s Public Buildings Service and USACE—two agencies with large amounts of obligations on construction—and two industry associations.

GAO is making two recommendations: that GSA’s Public Buildings Service and USACE each develop a strategy to routinely collect information on and monitor time frames for construction contract changes at the headquarters level.

Read the GAO report

Homeland Security Today
Homeland Security Todayhttp://www.hstoday.us
The Government Technology & Services Coalition's Homeland Security Today (HSToday) is the premier news and information resource for the homeland security community, dedicated to elevating the discussions and insights that can support a safe and secure nation. A non-profit magazine and media platform, HSToday provides readers with the whole story, placing facts and comments in context to inform debate and drive realistic solutions to some of the nation’s most vexing security challenges.

Related Articles

- Advertisement -

Latest Articles